02A - Excavation - Preliminary Estimate: $2,651,968
• General site grading
• Erosion Control
• Stone pavement base
• Construction fencing
• Site Utilities - sanitary, storm, dom. water & gas
• Temporary staging and construction entrance
• Misc. Demolition & Removals
• Snow removal
03A - Cast in Place Concrete - Preliminary Estimate: $2,586,901
• Excavation for foundations w backfill
• Cast in Place Concrete - building foundations, piers, etc.
• Cast in Place Concrete - slab on grade
• Stone base & vapor barrier at SOG
• Insulation at slab/foundation
• Cast in Place Concrete - slab on deck
• Cast in Place Concrete - curbs and walks
• Equipment pads
• Stair pan fill
• Cast in Place Concrete - heavy duty concrete paving
• Draintile
• Joint sealants associated with above
04A - Masonry - Preliminary Estimate: $6,066,375
• Masonry foundations
• Concrete masonry units
• Brick Veneer
• Cast stone
• Ground face block
• Installation of salvaged items
• Masonry reinforcing and grouting
• Masonry accessories, flashings, moisture barriers
• Receive, set, prime, & grout HM frames in masonry walls
• Receive & set loose lintels, bearing plates, imbeds
• Insulation at masonry walls
• Precast lintels F&I
• Masonry locker bases
• Joint sealants associated with above
• Waterproofing/vapor barriers associated with masonry
• Mock-ups & sample panels
05A - Metals - Preliminary Estimate: $3,261,395
• Structural steel
• Base plates and anchor bolts
• Open web steel joists
• Floor and roof deck
• Miscellaneous metals
• Loose lintels
• Roof frames
• Roof drain pans
• Steel stairs & railings
• Toilet partition supports
• Deck edge
• Safety cables & toe protection
• Access ladders
06A - Carpentry & Specialties - Preliminary Estimate: $3,355,044
• Exterior Rough Carpentry
• Interior Rough Carpentry, Backing & Sheathing
• Hollow Metal door & borrow light frames
• Door hardware
• Hollow metal doors
• Wood doors
• Overhead coiling doors
• Counter shutters
• Fire doors and shutters
• Walk-off mats
• Wall and corner guards
• Finish carpentry and trim
• Visual display boards
• Signage and directories
• Toilet partitions and screens
• Toilet accessories
• Cubicle curtains and track
• Wire mesh partitions
• Student lockers
• Athletic lockers
• Staff lockers
• Locker benches
• Metal storage shelving
• Display cases
• Residential appliances
• Fire extinguishers & cabinets
• Educational Equipment
• Projection screens
• Roller Window Shades
• Gymnasium Equipment
• Gymnasium Dividers
• Telescoping bleachers
• Curtains and Rigging
• Hydraulic Elevators
07A - Metal Wall Panels - Preliminary Estimate: $330,032
• Prefinished metal siding
• Joint sealants associated with above
• Prefinished aluminum louver
07B – Thermoplastic Polyolefin (TPO) Roofing - Preliminary Estimate: $1,538,986
• Low-sloped roofing system
• Protection board
• Insulation
• Flashing, counter-flashings & cant
• Wood blocking associated with roofing
• Metal copings
• Scuppers
• Roof hatches
• Joint sealants associated with above
08A - Glass & Glazing - Preliminary Estimate: $1,656,291
• Curtainwall systems
• Storefront
• Aluminum Entrances
• Associated hardware
• FRP entry doors
• Automatic door openers
• Spandrel panels
• Interior glazing
• Non-framed mirrors
09A - Interiors - Preliminary Estimate: $3,355,977
• Light gauge metal framing - interior and exterior
• Gypsum board assemblies
• Tiling
• Acoustic & DW ceilings
• Access doors
• Resilient sheet flooring
• Resilient tile flooring
• Athletic wood flooring
• Stage Wood Flooring
• Carpet
• Acoustic panels and treatments
• Painting
• FRP Panels
11A - Food Service Equipment - Preliminary Estimate: $758,625
• Food service equipment
• Serving lines
• Dishwashers
• Hood w/ fire suppression
• Coolers & freezers
12A - Casework - Preliminary Estimate: $709,114
• Educational casework
• Art-room casework
• Associated sinks, faucets
• Music room casework
• Instrument storage lockers
• Life Skills casework
• Media Center casework
• Science lab casework
• Fume hoods
• Resin tops & sinks
12B Loose Furnishings - FF&E - Preliminary Estimate: $1,825,919
• Educational furnishings
• Media center furnishings
• Office / administration furnishings
13A – Grandstands and Pressbox - Preliminary Estimate: $1,292,697
• Grandstand Seating System
• Grandstand foundations
• Pressbox
21A - Fire Suppression - Preliminary Estimate: $540,258
• Automatic sprinkler system
• Fire pump / jockey pump
• Balance and testing
• Hook-up range hood system
• Stand pipes
22A - Plumbing - Preliminary Estimate: $2,520,560
• Water service entry / meter
• Backflow preventers
• Hot/cold water service
• Pipe insulation
• Plumbing fixtures
• Mop sinks
• Shower units
• Grease traps
• Rough-in and connection of food service equipment
• Rough-in and connection to science equipment
• Emergency eyewash - facewash
• Sanitary Waste & Vent Systems
• Acid waste system
• Compressed Air Systems
• Storm water system
• Natural gas system
• Gas Service and Meter
• System Testing
23A - HVAC & Integrated Automation - Preliminary Estimate: $6,277,774
• Temporary heating requirements
• Heating Equipment & Distribution
• Cooling Equipment & Distribution
• Air Handling Equipment & Distribution
• Exhaust system
• Associated fire dampers, fire safing
• Heat recovery
• Temperature Control System
• Integrated building automation system
• Balance and testing
26A - Electrical - Preliminary Estimate: $5,403,948
• Temporary electric requirements
• Electric site utilities
• Service & switchboards
• Grounding
• Branch panels, circuits and wiring
• Emergency power requirements
• Technology system provisions (conduit stubs, cable tray, etc.)
• Lighting
• Theatrical lighting and controls
• Electrical scoreboards
• Rough-in for security system
• Site Lighting
• Fire Alarm System
28A - Security, Sound & Technology Systems - Preliminary Estimate: $2,985,462
• Communications & Telecom
• Clock system
• Paging/Central Sound
• Music room sound
• Gym & Stage sound system
• Student dining audio/video system
• Classroom audio/video system
• Electronic Safety & Security
32A - Final Site Development - Preliminary Estimate: $2,335,239
• Asphalt Paving
• Repair stone base
• Striping
• Topsoil spreading
• Landscaping
• Irrigation System
• Flagpole
• Site furnishings
• Site signage
• Fencing Install
32B – Synthetic Turf & Field Drainage System - Preliminary Estimate: $607,154
• Turf Field Base & Drainage
• Athletic Surfacing
• Synthetic Turf
• Track & Field Drainage Systems
32C - Track and Field Event Surfacing - Preliminary Estimate: $111,151