Amherst EVSD - PK-3 Elementary School

Amherst Exempted Village School District is building a new, 118,000 square foot Elementary School that will house 939 students in grades PK-3 and will be built in accordance with the Ohio School Design Manual.

  • Owner: Amherst Exempted Village School District
  • Co-Owner: Ohio Facilities Construction Commission
  • Architect: GPD Group
  • CM at Risk: ICON, LLC.
  • Location: Amherst, Ohio
  • Size: 118,000sf New PK-3 School
  • Value: $24 Million
  • Anticipated Bid Date: Site - Documents available February 16, 2018, Bids due March 2, 2018; New School - April 20, 2018
  • Construction: April 2018 - July 2019

PREQUALIFICATION OF SUBCONTRACTORS
ICON, LLC will be prequalifying subcontractors with criteria that has been pre-approved by the OFCC and the AEVSD in accordance with the guidelines set forth by the State of Ohio for CMaR contracting. More information and documents related to this project delivery format can be found at http://ofcc.ohio.gov/Documents.aspx. Although ICON, LLC will share information on bids received with the Co-Owners, this is not a public bid opening. More information on bid delivery will be issued with the bid packages to pre-qualified subcontractors. Questions on the process should be sent to amherstbidquestions@iconohio.com.

Contractors wishing to be considered for pre-qualification must do so by providing information on the web-tool at the link below. Information will be treated as confidential, and only shared with the members of ICON, AEVSD and the OFCC involved with the pre-qualification process.

SUBCONTRACTOR BID PACKAGES
ICON will be receiving bids from prequalified subcontractors on the bid packages listed below. It is also ICON’s intent to allow for the bidding of Combination Bids. We believe that this practice will allow for additional competition in the market, sustain the viability of local general contractors and allow the inclusion of smaller subcontractors who might otherwise be ineligible. Scope indicated below are for general information, only. Detailed scopes of work will be issued with each bid package.

03A – Cast-In-Place Concrete

• Excavation for foundations w backfill
• Cast in Place Concrete - building foundations, etc.
• Cast in Place Concrete - slab on grade
• Stone base & vapor barrier at SOG
• Insulation at slab/foundation
• Cast in Place Concrete - slab on deck
• Cast in Place Concrete - curbs and walks
• Equipment pads
• Stair pan fill
• Cast in Place Concrete - heavy duty concrete paving
• Draintile
• Joint sealants associated with above

04A – Masonry

• Masonry foundations
• Concrete masonry units
• Brick Veneer
• Masonry reinforcing and grouting
• Masonry accessories, flashings, moisture barriers
• Receive, set, prime, & grout HM frames in masonry walls
• Receive & set loose lintels, bearing plates, imbeds
• Joint sealants associated with above
• Waterproofing/vapor barriers associated with masonry
• Mock-ups & sample panels

05A – Metals, Structural Steel

• Structural steel
• Base plates and anchor bolts
• Open web steel joists
• Floor and roof deck
• Miscellaneous metals
• Loose lintels
• Roof frames
• Roof drain pans
• Steel stairs & railings
• Deck edge
• Safety cables & toe protection
• Access ladders

06A – Carpentry and Specialties

• Exterior Rough Carpentry
• Interior Rough Carpentry, Backing & Sheathing
• Hollow Metal door & borrow light frames
• Door hardware
• Hollow metal doors
• Wood doors
• Overhead coiling doors
. Overhead Garage doors and operators
• Counter shutters
• Fire doors and shutters
• Walk-off mats
• Wall and door protection
• Finish carpentry and trim
• Visual display boards
• Signage and directories
• Toilet partitions and screens
• Toilet accessories
• Cubicle curtains and track
• Wire mesh partitions
• Metal storage shelving
• Display cases
• Residential appliances
• Fire extinguishers & cabinets
• Projection screens
• Roller Window Shades
• Gymnasium Equipment
• Telescoping bleachers
• Curtains and Rigging
• Hydraulic Elevators

07A – Metal Wall Panels

• Formed Metal Wall Panels
• Metal Soffit Panels
• Composite Wall Panels

07B – Roofing, KEE & TPO

• Protection board
• Insulation
• Flashing, counter-flashings & cant
• Wood blocking associated with roofing
• Metal copings
• Scuppers
• Roof hatches
• Joint sealants associated with above

08A – Aluminum Framed Entrances and Storefronts, Glass and Glazing

09A – Interiors

• Light gauge metal framing - interior and exterior
• Gypsum board assemblies
• Ceramic Tiling
• Acoustic & DW ceilings
• Access doors
• Resilient athletic flooring
• Resilient tile flooring
• Athletic wood flooring
• Tile Carpeting
• Sound Absorbing Wall & Ceiling Units
• Painting

11A – Food Service Equipment

• Food service equipment
• Serving lines
• Dishwashers
• Hood w/ fire suppression
• Coolers & freezers

12A – Casework

• Plastic-Laminate-Faced casework
• Plastic-Laminate-Clad Countertops
• Solid Surfacing Countertops
• Associated sinks, faucets

21A – Fire Suppression

• Water Based Fire Suppression System
• Fire pumps
• Balance and testing
• Hook-up range hood system
• Stand pipes

22A – Plumbing

• Water service entry / meter
• Backflow preventers
• Hot/cold water service
• Pipe insulation
• Plumbing fixtures
• Mop sinks
• Shower units
• Grease traps
• Rough-in and connection of food service equipment
• Emergency eyewash - facewash
• Sanitary Waste & Vent Systems
• Storm water system
• Natural gas system
• Gas Service and Meter
• System Testing

23A – HVAC and Integrated Automation

• Temporary heating requirements
• Heating Equipment & Distribution
• Cooling Equipment & Distribution
• Air Handling Equipment & Distribution
• Exhaust system
• Associated fire dampers, fire safing
• Temperature Control System
• Integrated building automation system
• Balance and testing

26A – Electrical

• Temporary electric requirements
• Electric site utilities
• Service & switchboards
• Grounding
• Branch panels, circuits and wiring
• Emergency power requirements
• Technology system provisions (conduit stubs, cable tray, etc.)
• Lighting
• Theatrical lighting and controls
• Electrical scoreboards
• Rough-in for security system
• Site Lighting
• Fire Alarm System

28A – Communications, Security, Sound and Technology Systems

• Communications & Telecom
• Clock system
• First Responder Radio Communication System
• Paging/Central Sound
• Music room sound
• Gym & Stage sound system
• Student dining audio/video system
• Classroom audio/video system
• Electronic Safety & Security

32A – Site Development and Exterior Improvements

• Asphalt Paving
• Repair stone base
• Striping
• Topsoil spreading
• Landscaping
• Flagpole
• Site furnishings
• Site signage
• Chain Link Fencing Install